GP-12 checklist for the Jeep Recon EV ramp-up

GP-12 is the early production containment that protects a new program while the process proves itself: a dedicated inspection on top of normal controls. With the Jeep Recon EV entering production at Stellantis Toluca in Q2 2026, suppliers should have their GP-12 station defined before first shipments.

Published: July 3, 2026

When does GP-12 apply on a new program?

GP-12 covers the launch window: pre-production builds, ramp-up and the early weeks of regular production, until the data shows the process is stable and the OEM agrees to close it. On a program like the Recon EV, that window is when scorecards are set and when a single escape does the most damage, because every function at the plant is watching launch parts. Treat GP-12 as a data engine rather than a checkbox: the same records that keep defects off the line become the evidence that closes containment early. Suppliers who staff it properly from day one usually exit weeks sooner than those who improvise the station after the first concern.

What goes into the GP-12 station?

Checklist itemWhat good looks like
Written criteria sheetDefect definitions agreed with your team and the SQE before first shipment
Boundary samplesPhysical or photo standards for pass and fail at the station
Trained inspectorsNamed, trained people per shift, not whoever is free
Data sheetsCounts per lot with date, shift and inspector recorded daily
IdentificationGP-12 label on certified shipments so the plant can trace them
Escalation pathWho calls whom within the hour when a defect is found

How do you exit GP-12 cleanly?

Exit comes from evidence: a run of clean lots across an agreed window, capability data on the critical features, and closed actions on anything the station caught. Package the daily sheets into a weekly summary so the closure review is a formality rather than a debate. IDS staffs and documents GP-12 and Safe Launch for Recon EV suppliers at Stellantis Toluca, building the criteria with your team and reporting daily. Launching soon? Request a quote and we confirm a plan within 1 hour.

FAQ Frequently asked questions

Is GP-12 mandatory on a new launch?

On programs where the OEM requires it, yes: GP-12 early production containment applies through launch and ramp-up until the OEM agrees the process is stable and closes it.

Who staffs the GP-12 station?

The supplier is responsible, and many use trained third-party inspectors so production staff stay on production. IDS provides named, trained inspectors per shift at Stellantis Toluca.

When should GP-12 planning start for the Recon EV?

Before first shipments. The Jeep Recon EV enters production at Stellantis Toluca in Q2 2026, so criteria, boundary samples and staffing should be agreed ahead of the ramp.